Upgrades to the MPS Server Room are now complete.  A tour of the facility for affiliated faculty and personnel took place on August 22nd, and final heat/load testing is underway.  Once that is complete, we will be able to announce an opening/availability date.  We hope to be back in the facility right around the time classes begin.  

Humidification has been added to both the existing Liebert and the new 5-ton capacity unit.  Variable fan speed control and reheater units have also been added to the existing Liebert so that high humidity can effectively be removed from the facility.  In addition, hot aisle containment has been added to the racks to make cooling more efficient.

Watch this space for information on when the facility has been officially reopened.